§ 50-95. Review and approval.  


Latest version.
  • (a)

    The objecting agencies shall, within 20 days of the date of receiving their copies of the final plat, notify the subdivider and all other approving and objecting agencies of any objections. If there are no objections, they shall so certify on the face of the copy of the plat and shall return that copy to the village clerk. If an objecting agency fails to act within 20 days, it shall be deemed to have no objection to the plat.

    (b)

    If the final plat is not submitted within 36 months of the last required approval of the preliminary plat, the village board may refuse to approve the final plat or may extend the time for submission of the final plat, as provided in Wis. Stats. § 236.11(1)(b).

    (c)

    The plan commission shall, within 30 days of the date of filing of the final plat with the village clerk, recommend approval or rejection of the plat and shall transmit the final plat and application along with its recommendations to the village board.

    (d)

    The plan commission shall, at the time it recommends approval or rejection of a plat to the village board, give at least ten days' prior written notice of its recommendation to the clerk of any local government within 1,000 feet of the plat, but failure to give such notice shall not invalidate the plat.

    (e)

    The village board shall, in accordance with Wis. Stats. § 236.11(2), within 60 days of the date of filing the original plat with the village clerk, approve or reject such plat, unless time is extended by agreement with the subdivider. The village board may act on the plat at the same meeting at which the plan commission makes its recommendation. One copy of the plat shall thereupon be returned to the subdivider with the date and action endorsed thereon. If the plat is rejected, the reasons shall be stated in the minutes of the meeting and a written statement of the reasons forwarded to the subdivider. One copy each of the plat and letter shall be placed in the village board's permanent file. The village board shall not inscribe its approval on the final plat unless the village clerk certifies on the face of the plat that the copies were forwarded to objecting agencies as required herein, with the date they were forwarded, and that no objections have been filed within 20 days or, if filed, that they have been met.

    (f)

    Failure of the village board to take action on the plat within 60 days, the time having not been extended and no unsatisfied objections having been filed, and all fees payable by the subdivider having been paid, shall constitute approval of the plat.

(Ord. No. 802-13, § 1(Att.), 4-22-2013)